Time study and standard time
Stopwatch time study from elements to standard time: rating, allowances on normal time vs on the working day, and the number of cycles for a given confidence and accuracy.
Drafted with Aria, reviewed by the AiCanCode.org team. Spotted an error? Use Give Feedback at the bottom of the page.
Why it matters
Standard time is the number behind almost every plant decision: how many workers and machines a line needs, what a part costs, what the delivery promise is and what incentive a worker earns. Stopwatch time study is the most widely used way to set it for repetitive manual and machine-paced jobs, so you must know how to get from raw readings to a defensible standard.
Key ideas
Time study is a work-measurement technique for recording the times and rates of working for the elements of a specified job under specified conditions, and analysing the data to obtain the time needed to do the job at a defined level of performance. It should be done after method study, on the improved and standardised method.
Qualified worker and standard performance. The standard is set for a qualified worker (trained, with the physical attributes and skill for the job) working at standard performance: the rate a qualified worker naturally achieves without over-exertion over a working day, given motivation. On the British Standard scale this is 100; on the older 60–80 scale it is 80.
Procedure
- Select the job and the worker (an average, qualified, cooperative operator); record the method, tools, materials and conditions.
- Break the job into elements: short, distinct parts with clear break points. Separate manual from machine elements, constant from variable, repetitive from occasional, and record foreign elements (not part of the job) separately so they can be excluded.
- Time each element with a stopwatch (continuous or snap-back/fly-back method) or electronic timer, and rate the worker's pace at the same time.
- Decide the number of cycles needed for the required accuracy.
- Compute the normal (basic) time, then add allowances to get the standard time.
Performance rating adjusts observed time to what a qualified worker at standard pace would take. Methods: speed (pace) rating, where the observer judges pace against the 100 standard; the Westinghouse (levelling) system, which adds factors for skill, effort, conditions and consistency to 1; synthetic rating, which compares observed times of some elements with predetermined (PMTS) times for them; and objective rating. A rating of 120 % means the worker was faster than standard, so normal time is longer than observed time.
Allowances are extra time added to normal time: personal needs; basic and variable fatigue (posture, force, heat, noise, monotony); unavoidable delays; and policy or special allowances (contingency, set-up, machine interference). Total allowances usually fall in the range of about 10–20 %, but the exact values come from the company's or ILO allowance tables.
Allowances defined two ways. If allowance is a percentage of normal time, multiply. If it is a percentage of the total working time (shift), divide by (1 − A). Read the question carefully; the second gives a larger standard time.
Formulas
Observed (selected) time OT = Σx / n
- x = element time from each cycle (min); n = number of cycles; foreign elements and abnormal readings removed.
Normal (basic) time NT = OT × R / 100
- R = performance rating (%), standard pace = 100.
Standard time ST = NT × (1 + A) when A is a fraction of normal time.
Standard time ST = NT / (1 − A) when A is a fraction of the total working time.
Number of cycles N′ = [ 40 √(nΣx² − (Σx)²) / Σx ]²
- For 95 % confidence and ±5 % accuracy from n trial readings. General form
N′ = (z·s / (k·x̄))², where z = 1.96 for 95 % confidence, s = sample standard deviation, k = accuracy fraction, x̄ = mean.
Output per shift = Available time / ST
Worked examples
Example 1 (standard). A job has three elements with average observed times 0.25, 0.60 and 0.15 min, rated 120 %, 90 % and 100 %. Allowances are 15 % of normal time. Find the standard time and the standard output in a 480-min shift.
- Element normal times:
0.25 × 1.20 = 0.30,0.60 × 0.90 = 0.54,0.15 × 1.00 = 0.15 min. NT = 0.30 + 0.54 + 0.15 = 0.99 min.ST = 0.99 × 1.15= 1.139 min per unit.Output = 480 / 1.1385= 421 units per shift.
Example 2 (GATE level). Ten trial readings of an element (min): 0.40, 0.48, 0.36, 0.50, 0.42, 0.46, 0.38, 0.52, 0.44, 0.40. (a) How many readings are needed for 95 % confidence and ±5 % accuracy? (b) With a rating of 110 % and allowances of 12 %, find the standard time if the allowance is (i) 12 % of normal time and (ii) 12 % of total working time.
Σx = 4.36,Σx² = 1.9264, n = 10.nΣx² − (Σx)² = 19.264 − 19.0096 = 0.2544;√0.2544 = 0.5044.N′ = (40 × 0.5044 / 4.36)² = (4.627)²= 21.4, so 22 readings; 12 more are needed.OT = 4.36 / 10 = 0.436 min;NT = 0.436 × 1.10 = 0.4796 min.- (i)
ST = 0.4796 × 1.12= 0.537 min. - (ii)
ST = 0.4796 / (1 − 0.12) = 0.4796 / 0.88= 0.545 min.
Common mistakes
- Dividing by the rating instead of multiplying (a fast worker, R > 100 %, gives NT > OT).
- Mixing the two allowance definitions; check whether the percentage is of normal time or of the shift.
- Adding allowances before rating; rating applies to observed time only, allowances to normal time.
- Rating machine-controlled elements: an automatic machine time is not rated (R = 100 %).
- Including foreign elements or freak readings in the average.
- Rounding N′ down; always round the number of cycles up.
For GATE PI
Very common: normal and standard time from observed time, rating and allowances (both allowance definitions), output per shift, and the number of observations for a given confidence and accuracy. Also one-mark questions on rating systems, types of elements and allowances. Practise reading which basis the allowance uses and carrying three significant figures.
Quick check
- Observed time 2.0 min, rating 90 %, allowance 10 % of normal time. Standard time?
- A worker rated 125 % takes 0.8 min. What is the normal time?
- Normal time 1.0 min, allowance 20 % of the working day. Standard time?
- Which rating system uses skill, effort, conditions and consistency?
Answers: 1. 2.0 × 0.9 × 1.1 = 1.98 min; 2. 1.0 min; 3. 1.0 / 0.8 = 1.25 min; 4. Westinghouse (levelling) system.
See it move
All Production animationsAdjust the observed time, performance rating, and allowances to see how they affect the basic and standard time for a task.
Equations used
- Basic Time = Observed Time × Performance Rating
- Standard Time = Basic Time + Allowances
Interview questions
All Work Systems and Facility Design interview questionsTry answering each one aloud before you open it.
1.What is a time study in the context of work systems and facility design?Concept
A time study is a method used to determine the time required for a qualified worker to complete a specific task at a defined level of performance. It involves observing and recording the time taken for each element of a task, analyzing the data, and establishing a standard time for the task.
2.Explain the concept of standard time in industrial engineering.Concept
Standard time is the time required for a qualified worker to complete a task under normal working conditions, including allowances for rest, fatigue, and delays. It is calculated by adding allowances to the normal time, which is the observed time adjusted for the worker's performance rating.
3.Why is time study important in facility design?Application
Time study is important in facility design because it helps in determining the most efficient way to perform tasks, which can lead to improved productivity and reduced costs. By understanding the time required for each task, facilities can be designed to optimize workflow, reduce bottlenecks, and ensure that resources are allocated effectively.
4.What happens if allowances are not included in the calculation of standard time?Application
If allowances are not included in the calculation of standard time, the time set for tasks will be underestimated. This can lead to unrealistic expectations for worker performance, increased fatigue, higher error rates, and potentially lower quality of work. It may also result in poor worker morale and increased turnover.
5.How does a time study differ from a motion study?Concept
A time study focuses on measuring the time taken to perform a task, while a motion study analyzes the movements involved in performing a task to identify and eliminate unnecessary motions. Both studies aim to improve efficiency, but they focus on different aspects of the work process.
6.Explain how performance rating is used in time studies.Concept
Performance rating is used in time studies to adjust the observed time to reflect the standard performance level. It involves assessing the speed and skill of the worker compared to a standard or average worker. The observed time is multiplied by the performance rating to calculate the normal time for the task.
7.Why might a company choose to conduct a time study instead of relying on historical data?Application
A company might choose to conduct a time study instead of relying on historical data to obtain more accurate and current information about task performance. Historical data may be outdated or not reflect current working conditions, equipment, or processes. Time studies provide precise data that can be used to set realistic standards and improve efficiency.
8.What are some common challenges faced during time studies?Application
Common challenges during time studies include worker resistance, observer bias, variability in task performance, and ensuring that the observed conditions are representative of normal working conditions. Accurate measurement and analysis require careful planning and execution to overcome these challenges.
9.Calculate the standard time for a task if the observed time is 5 minutes, the performance rating is 110%, and the allowance is 15%.Numerical
- Calculate the normal time: Normal Time = Observed Time × Performance Rating = 5 min × 1.10 = 5.5 min.
- Calculate the standard time: Standard Time = Normal Time × (1 + Allowance) = 5.5 min × (1 + 0.15) = 6.325 min.
10.A task has an observed time of 8 minutes and a performance rating of 95%. If the standard time is 9.2 minutes, what is the allowance percentage?Numerical
- Calculate the normal time: Normal Time = Observed Time × Performance Rating = 8 min × 0.95 = 7.6 min.
- Use the standard time formula to find the allowance: Standard Time = Normal Time × (1 + Allowance).
- 9.2 min = 7.6 min × (1 + Allowance).
- Allowance = (9.2 / 7.6) - 1 = 0.2105 or 21.05%.
Finished this topic? Mark it so your progress, study plan and readiness keep up.
Stuck on something here?