  1. Unit 1: Safety and Prevention of Accidents

    8 hours

    Safety terminology; the Indian Electricity Act and statutory regulations; IS and IEC safety standards; do's and don'ts for substation operators; causes of electrical accidents and factors in shock severity; rescue and artificial respiration; preventing electrical fires and using extinguishers.

    Examined in the 100-mark end-semester paper

    • Principles of electrical safety and accident prevention
    • The Electricity Act, 2003
    • Medical effects of electric shock
    • IE Rules on first aid and firefighting
  2. Unit 2: Estimating and Conductor Size Calculations

    8 hours

    Purpose and steps of estimating, price catalogues and schedules of rates; conductor size by current capacity, voltage drop, temperature rise and minimum size per IS/IEC; sizing for domestic wiring, underground cables and ACSR overhead lines.

    Examined in the 100-mark end-semester paper

    • Principles of estimating and costing
    • Cable and conductor sizing
    • Current-carrying capacity and grouping of cables
    • Permissible voltage drop for lighting and industrial loads
    • Estimating residential and commercial wiring
    • Conductor sizing for overhead lines with ACSR
  3. Unit 3: Electrical Installation

    8 hours

    Designing machine foundations and their dimensions; levelling and aligning shafts of direct and indirect drives and the effects of misalignment; installing rotating machines per IS 900 and IEC; purpose of earthing, pipe and plate earthing.

    Examined in the 100-mark end-semester paper

    • Machine foundations, levelling and shaft alignment
    • Equipment and neutral earthing
    • Earth electrodes and earth resistance
  4. Unit 4: Testing of Rotating Machines, Transformer, and Insulation

    10 hours

    Purpose of testing and IS/IEC standards; pre-commissioning tests; routine, type, special and supplementary tests on transformers and rotating machines; induced over-voltage and impulse withstand tests; insulation classes and the life of insulation; transformer oil, its contaminants and the acidity, flash point, crackle, sludge and dielectric strength tests.

    Examined in the 100-mark end-semester paper

    • Type, routine and special tests on transformers
    • Heat run and high-voltage withstand tests
    • Transformer oil testing and reconditioning
  5. Unit 5: Maintenance of Rotating Machines, Transformer and Insulation

    7 hours

    Routine, preventive and breakdown maintenance compared; developing a preventive maintenance schedule and what affects it; total productive maintenance; routine and preventive maintenance of transformers.

    Examined in the 100-mark end-semester paper

    • Maintenance strategies
    • Preventive maintenance of transformers and motors
    • Insulation deterioration and polarisation index
  6. Unit 6: Electrical Insulation

    7 hours

    Requirements and types of solid, liquid and gaseous insulation and their uses; thermal classes Y to C; dielectric strength, loss and constant; breakdown in solid, liquid and gas insulation; insulation resistance with a megger and dielectric strength tests.

    Examined in the 100-mark end-semester paper

    • Insulating materials in power apparatus
    • Temperature rise and rating of machines
    • Breakdown in solid dielectrics
    • Insulation resistance testing