Capacity planning

Design and effective capacity, utilisation and efficiency, capacity cushion, machines required with scrap, RCCP and CRP load checks, expansion strategies and bottlenecks.

Drafted with Aria, reviewed by the AiCanCode.org team. Spotted an error? Use Give Feedback at the bottom of the page.

Why it matters

A schedule that ignores capacity is a wish list. Capacity planning decides how many machines, people and shifts are needed, checks whether the master schedule and MRP orders can actually be produced, and shows which work centre is the bottleneck. Too little capacity means late orders and lost sales; too much ties up capital in idle equipment.

Key ideas

Capacity is the maximum rate of output of a facility, measured in output units (cars per day, tonnes per month) or, for mixed products, in input units (machine-hours or labour-hours available per period).

Three levels of capacity.

  • Design (theoretical) capacity – the maximum output under ideal conditions, as designed.
  • Effective capacity – the maximum output possible given product mix, set-ups, scheduled maintenance, breaks, quality standards and similar planned allowances. It is always ≤ design capacity.
  • Actual output – what is really produced, after unplanned losses (breakdowns, absenteeism, material shortages, rework). Always ≤ effective capacity.

Utilisation and efficiency.

  • Utilisation = actual output ÷ design capacity.
  • Efficiency = actual output ÷ effective capacity. Efficiency can look good while utilisation is poor, because effective capacity already excludes planned losses.

Capacity cushion = (capacity − average demand) ÷ capacity. Plants with uncertain or variable demand, or many products, keep a larger cushion; continuous process plants keep a small one because idle capacity is very expensive.

Hierarchy of capacity planning (matches the planning hierarchy).

  • Resource requirements planning (long range) – checks the aggregate plan against plant, equipment and workforce; leads to expansion decisions.
  • Rough-cut capacity planning (RCCP) (medium range) – checks the MPS against critical work centres using overall factors (CPOF), bills of capacity or resource profiles.
  • Capacity requirements planning (CRP) (short range) – takes the MRP planned and released orders, routings and set-up/run times, and builds a time-phased load profile for every work centre.
  • Input/output control (very short range) – compares planned with actual input and output at each work centre to control queues.

Responding to a load imbalance. Increase capacity (overtime, extra shift, alternate routing, subcontracting, more operators) or reduce load (reschedule orders, split lots, change the MPS). Underloads are handled by pulling work forward or reducing hours.

Long-term expansion strategies.

  • Lead – add capacity ahead of demand; protects service and market share, risks idle capacity.
  • Lag – add capacity after demand has grown; high utilisation, risks lost sales.
  • Match (average) – add in small steps around the demand trend. Economies of scale, bottleneck balancing, and break-even and decision-tree analysis are used to choose the size and timing of increments.

Bottleneck. The resource with the highest load relative to its capacity limits the output of the whole system; an hour lost there is an hour lost for the plant. Adding capacity elsewhere does not raise output.

Formulas

Utilisation = actual output / design capacity Efficiency = actual output / effective capacity Actual output = design capacity × utilisation = effective capacity × efficiency

  • All in units per period (or hours per period); results as fractions or %.

Capacity cushion = (capacity − average demand) / capacity

  • Fraction or %.

Available hours per machine = days × shifts × hours per shift × efficiency (or availability)

  • In hours per period; efficiency or availability is a fraction.

Number of machines N = (Q_good / (1 − s)) · t / H_avail

  • Q_good = good parts required per period (units), s = scrap fraction, t = standard time per part (h/unit), H_avail = productive hours per machine per period (h). Round N up to the next whole machine.

Load on work centre j (period t) = Σ (set-up time + quantity × run time per unit) over all orders at j in t Load (RCCP, overall factors) = Σ MPS_i × total hours per unit of i × historical share of work centre j

  • Compare load (h) with available capacity (h).

Worked examples

Example 1 (standard) – utilisation, efficiency and machines required. (a) A line has design capacity 1000 units/week, effective capacity 850 units/week and actual output 800 units/week.

  1. Utilisation = 800/1000 = 80 %.
  2. Efficiency = 800/850 = 94.1 %. (b) A part is needed at 60,000 good pieces per year. Standard time 6 min per piece, expected scrap 4 %, plant works 250 days × 2 shifts × 8 h, machine efficiency 85 %.
  3. Pieces to start = 60,000/(1 − 0.04) = 62,500 pieces.
  4. Hours required = 62,500 × (6/60) = 6250 h.
  5. Productive hours per machine = 250 × 2 × 8 × 0.85 = 3400 h.
  6. N = 6250/3400 = 1.84, so 2 machines are needed (utilisation about 92 %).

Example 2 (GATE level) – rough-cut check by overall factors. Product A needs 0.8 h and product B needs 1.2 h of total direct labour per unit. Historically 60 % of hours fall on work centre WC1 and 40 % on WC2. Weekly capacity: WC1 = 100 h, WC2 = 70 h. MPS for weeks 1–3: A = 100, 120, 80 units; B = 50, 60, 90 units.

  1. Total hours per week = 0.8 × A + 1.2 × B.
    • Week 1: 0.8 × 100 + 1.2 × 50 = 80 + 60 = 140 h.
    • Week 2: 0.8 × 120 + 1.2 × 60 = 96 + 72 = 168 h.
    • Week 3: 0.8 × 80 + 1.2 × 90 = 64 + 108 = 172 h.
  2. WC1 load (60 %): 84.0, 100.8, 103.2 h. WC2 load (40 %): 56.0, 67.2, 68.8 h.
  3. Compare: WC2 is within 70 h every week. WC1 is within 100 h in week 1 but overloaded by 0.8 h in week 2 and 3.2 h in week 3.
  4. Since WC1 has 16 h spare in week 1, the scheduler can pull about 4 h of work forward or authorise 4 h of overtime; the MPS is then feasible. Over three weeks WC1 total load = 288 h ≤ 300 h available, so the problem is timing, not total capacity.

Common mistakes

  • Swapping utilisation and efficiency, or dividing by the wrong capacity.
  • Forgetting scrap: machines must process the good quantity divided by (1 − s), not multiplied by (1 + s) (the second is only an approximation).
  • Rounding the number of machines down; capacity must be at least the requirement.
  • Mixing minutes and hours, or days per year with shifts per day.
  • Treating total load over a horizon as enough when individual periods are overloaded.
  • Adding capacity at a non-bottleneck station and expecting system output to rise.

For GATE PI

Expect short numericals on design and effective capacity, utilisation and efficiency, number of machines needed with scrap and efficiency, and load versus capacity at work centres for a given schedule. Conceptual items cover RCCP vs CRP, lead/lag strategies and bottlenecks. Practise unit conversions and always round machine counts up.

Quick check

  1. Effective capacity 450 units/day, actual output 405 units/day, design capacity 500 units/day. Find utilisation and efficiency.
  2. 9000 good parts are needed per month with 10 % scrap. How many parts must be started?
  3. A machine has 400 h per month available and a job needs 1500 h. How many machines are needed?
  4. Which capacity check uses MRP planned orders and routings?

Answers: 1. 81 % and 90 %. 2. 9000/0.9 = 10,000 parts. 3. 1500/400 = 3.75, so 4 machines. 4. Capacity requirements planning (CRP).

Try answering each one aloud before you open it.

  1. 1.What is capacity planning in production and operations management?Concept

    Capacity planning decides how much output capability (machines, labour, shifts, space) is needed and when, so that planned production can actually be made. Long-range it sizes plants and equipment; medium-range rough-cut capacity planning checks the master schedule against critical work centres; short-range capacity requirements planning builds work-centre load profiles from MRP orders and routings. The aim is to meet demand on time without carrying expensive idle capacity.

  2. 2.Explain the difference between long-term and short-term capacity planning.Concept

    Long-term capacity planning focuses on strategic decisions that affect the overall capacity of an organization, such as investments in new facilities or equipment. Short-term capacity planning, on the other hand, deals with operational decisions that optimize the use of existing resources to meet immediate demand, such as scheduling and workforce management.

  3. 3.Why is capacity planning important in manufacturing?Application

    Capacity planning is crucial in manufacturing because it ensures that production resources are used efficiently, helps in meeting customer demand on time, reduces costs by avoiding overproduction or underutilization, and supports strategic decision-making for future growth and expansion.

  4. 4.What are the key factors to consider in capacity planning?Concept

    Key factors in capacity planning include demand forecasting, production lead times, resource availability, technology and equipment capabilities, labor skills, and financial constraints. These factors help in determining the optimal capacity level to meet demand efficiently.

  5. 5.How does capacity planning affect supply chain management?Application

    Capacity planning affects supply chain management by ensuring that production levels align with supply chain capabilities. It helps in maintaining inventory levels, optimizing logistics, and coordinating with suppliers to ensure timely delivery of raw materials and components, thereby reducing bottlenecks and improving overall efficiency.

  6. 6.What happens if a company underestimates its capacity requirements?Application

    If a company underestimates its capacity requirements, it may face production bottlenecks, delayed deliveries, and unsatisfied customers. This can lead to lost sales, damage to the company's reputation, and increased costs due to overtime or expedited shipping to meet demand.

  7. 7.Describe the role of technology in capacity planning.Concept

    Technology plays a significant role in capacity planning by providing tools for accurate demand forecasting, real-time monitoring of production processes, and data analysis for decision-making. Advanced software solutions can simulate different scenarios, optimize resource allocation, and improve overall efficiency in capacity management.

  8. 8.What is the impact of seasonal demand fluctuations on capacity planning?Application

    Seasonal demand fluctuations can significantly impact capacity planning by requiring adjustments in production schedules, workforce levels, and inventory management. Companies must anticipate these changes and plan accordingly to ensure they can meet peak demand periods without overextending resources during off-peak times.

  9. 9.A factory produces 500 units per day with a maximum capacity of 600 units. If demand increases by 20%, what should be the new production level to meet demand?Numerical

    Current production is 500 units per day. A 20% increase in demand means an additional 100 units (500 * 0.20). Therefore, the new production level should be 600 units per day to meet the increased demand.

  10. 10.Calculate the utilization rate if a plant operates at 450 units per day with a capacity of 600 units.Numerical

    Utilization rate is calculated as (Actual Output / Maximum Capacity) * 100. Here, it would be (450 / 600) * 100 = 75%.

Finished this topic? Mark it so your progress, study plan and readiness keep up.

Stuck on something here?