  1. Unit 1: Overview of Restructured Power System

    7 hours

    Regulation and deregulation, vertically integrated and deregulated industry, market models, market clearing price, the independent system operator and ancillary services.

    Examined in the 60-mark end-semester paper, and in the mid-semester exam if it is taught by then

    • Need for deregulation
    • Restructured versus vertically integrated utilities
    • Restructuring models
    • Market clearing price
    • Independent system operator and ancillary services
  2. Unit 2: Economic Considerations

    7 hours

    Consumer and supplier behaviour, demand and supply elasticity, short- and long-run costs; electricity pricing in generation, transmission and distribution, marginal and opportunity costs, ABT, tariff setting and HT/LT tariffs.

    Examined in the 60-mark end-semester paper, and in the mid-semester exam if it is taught by then

    • Elasticity and market equilibrium
    • Costs of production in the power sector
    • Tariff setting
  3. Unit 3: Global Models of Restructured Power System

    6 hours

    Market evolution in the UK, USA, South America, the Nordic pool, China, PJM and New York.

    Examined in the 60-mark end-semester paper, and in the mid-semester exam if it is taught by then

    • Pool and bilateral trading
    • Spot and forward electricity markets
  4. Unit 4: Indian Power Market Evolution

    7 hours

    The Electricity Act 2003 and national policies; the Ministry of Power, CEA, CERC, state commissions and load dispatch centres; ABT tariff; the Indian Power Exchange.

    Examined in the 60-mark end-semester paper, and in the mid-semester exam if it is taught by then

    • Electricity Act 2003
    • Institutions of the Indian power sector
    • Power exchanges and day-ahead markets
  5. Unit 5: Transmission Pricing and Congestion Management

    7 hours

    Transmission price components and pricing mechanisms, power tracing, network usage and loss allocation; congestion and its management.

    Examined in the 60-mark end-semester paper, and in the mid-semester exam if it is taught by then

    • Transmission pricing methods
    • Congestion management
  6. Unit 6: OASIS

    6 hours

    Structure of OASIS, pooling of information, transfer capability and ATC, TTC, TRM and CBM.

    Examined in the 60-mark end-semester paper, and in the mid-semester exam if it is taught by then

    • Available transfer capability
    • OASIS and transfer capability margins