Production Planning and Operations Management — formula sheet
Production & Industrial Engineering · GATE PI · SI units. Drafted with Aria, checked by the AiCanCode.org team.
Production Systems and the Planning Hierarchy
T_b = T_su + Q·T_c— Batch time (h); T_su is set-up time (h), Q is batch size (units), T_c is cycle time per unit (h/unit).R_p = Q / T_b— Average production rate (units/h) of a batch process.PC = n·S_w·H_s·R_p— Production capacity (units/period); n is number of work centres, S_w is shifts per period, H_s is hours per shift (h).Q_BE = (F₂ − F₁) / (v₁ − v₂)— Break-even volume between two processes (units/year); F is fixed cost (₹/year), v is variable cost (₹/unit), F₂ > F₁ and v₂ < v₁.
Forecasting: Moving Average and Exponential Smoothing
F(t+1) = [D(t) + D(t−1) + … + D(t−n+1)] / n— Simple moving average forecast (units); D is actual demand (units), n is number of periods.F(t+1) = Σ wᵢ·D(t−i+1), Σ wᵢ = 1— Weighted moving average; wᵢ are weights (dimensionless), largest on the most recent period.F(t+1) = F(t) + α·[D(t) − F(t)] = α·D(t) + (1 − α)·F(t)— Simple exponential smoothing; α is smoothing constant (0 < α < 1).α ≈ 2 / (n + 1)— Smoothing constant with the same average data age as an n-period moving average.F(t+1) = L(t) + T(t)— Holt's trend-adjusted forecast; L(t) = α·D(t) + (1 − α)·[L(t−1) + T(t−1)], T(t) = β·[L(t) − L(t−1)] + (1 − β)·T(t−1).
Forecasting: Regression and Forecast Error Measures
y = a + b·x— Linear regression forecast; y is demand (units), x is period number or causal variable, a is intercept (units), b is slope (units per unit of x).b = (n·Σxy − Σx·Σy) / (n·Σx² − (Σx)²), a = ȳ − b·x̄— Least-squares slope and intercept; n is number of data pairs.e(t) = D(t) − F(t)— Forecast error (units); positive means under-forecast.MAD = Σ|e(t)| / n— Mean absolute deviation (units).MSE = Σe(t)² / n— Mean squared error (units²).MAPE = (100/n)·Σ|e(t)| / D(t)— Mean absolute percentage error (%); undefined if any D(t) = 0.TS = Σe(t) / MAD— Tracking signal (number of MADs); typical control limits ±4.σ ≈ 1.25·MAD— Standard deviation of forecast error for normally distributed errors.
Aggregate Production Planning
I(t) = I(t−1) + P(t) − D(t)— Closing inventory (units; negative means backorder); P is production (units), D is demand (units).P_level = [ΣD(t) + I_end − I_0] / N— Level production rate (units/period); I_0 opening and I_end required closing inventory, N number of periods; check cumulative production ≥ cumulative demand.TC = Σ[c_r·R + c_o·O + c_s·S + c_h·I⁺ + c_b·I⁻ + c_H·H + c_F·F]— Total plan cost (₹); R, O, S are regular, overtime and subcontracted units, I⁺ inventory, I⁻ backorders, H and F workers hired and fired, c are the corresponding unit costs.cell cost (made in i, used in j) = c_i + c_h·(j − i)— Transportation-method cost (₹/unit), j ≥ i when backorders are not allowed.
Master Production Schedule
Requirement(t) = max[F(t), CO(t)]— Requirement used in the MPS (units); F is forecast, CO is booked customer orders.POH(t) = POH(t−1) + MPS(t) − Requirement(t)— Projected on-hand inventory (units); schedule a lot whenever POH would fall below safety stock.ATP(1) = OH + MPS(1) − ΣCO(1 … k−1)— Available-to-promise in week 1 (units); OH is on-hand, k is the next week with an MPS receipt.ATP(k) = MPS(k) − ΣCO(k … m−1)— Discrete ATP in an MPS week k (units); m is the following MPS week.
Material Requirements Planning and Lot Sizing
GR(child, t) = Σ PORel(parent, t) × usage per parent— Gross requirement of a component (units).NR(t) = max[0, GR(t) + SS − POH(t−1) − SR(t)]— Net requirement (units); SS safety stock, SR scheduled receipt.PORel(t − L) = PORec(t)— Planned order release offset by lead time L (periods).POQ = EOQ / d̄— Periodic order quantity (periods to cover, rounded); d̄ is average demand per period (units/period).EPP = S / h— Economic part-period (unit·periods) for part-period balancing; S is ordering cost (₹/order), h is holding cost (₹/unit·period).
Capacity Planning
Utilisation = actual output / design capacity— Fraction or %; outputs in units/period.Efficiency = actual output / effective capacity— Fraction or %.Capacity cushion = (capacity − average demand) / capacity— Fraction or %.N = [Q_good / (1 − s)]·t / H_avail— Number of machines (round up); Q_good good parts per period (units), s scrap fraction, t standard time (h/unit), H_avail productive hours per machine per period (h).
Single-Machine Sequencing: SPT, EDD and Moore's Rule
Lᵢ = Cᵢ − dᵢ, Tᵢ = max(0, Lᵢ)— Lateness and tardiness (h); C is completion time, d is due date.F̄ = ΣFᵢ / n— Mean flow time (h); with all jobs ready at zero, Fᵢ = Cᵢ. Minimised by SPT.N̄ = ΣFᵢ / Σpᵢ— Average number of jobs in the system; p is processing time (h).Order by increasing pᵢ / wᵢ— Weighted SPT (Smith's rule), minimises weighted mean flow time; EDD minimises maximum lateness; Moore's algorithm minimises the number of tardy jobs.
Flow Shop Scheduling: Johnson's Rule
Jobs with aᵢ ≤ bᵢ first in increasing aᵢ, then jobs with aᵢ > bᵢ in decreasing bᵢ— Johnson's rule for minimum makespan on two machines; a and b are times on M1 and M2 (h).C₂(k) = max[C₁(k), C₂(k−1)] + b(k)— Finish time on M2 of the job in position k (h); C₁(k) = C₁(k−1) + a(k).Idle time on M2 = C_max − Σbᵢ— Idle time (h); C_max is the makespan.gᵢ = aᵢ + bᵢ, hᵢ = bᵢ + cᵢ— Three-machine reduction, optimal when min aᵢ ≥ max bᵢ or min cᵢ ≥ max bᵢ.
Inventory Costs and the EOQ Model
TC(Q) = (D/Q)·S + (Q/2)·H + D·C— Total annual cost (₹/year); D annual demand (units/year), Q order quantity (units), S ordering cost (₹/order), H holding cost (₹/unit·year), C unit price (₹/unit).Q* = √(2·D·S / H)— Economic order quantity (units).TC* = √(2·D·S·H)— Minimum annual ordering + holding cost (₹/year); ordering cost = holding cost at Q*.TC(Q) / TC* = ½·(Q/Q* + Q*/Q)— Cost penalty for a non-optimal lot size.ROP = d·L— Reorder point (units) with constant demand d (units/day) and lead time L (days); if L exceeds the cycle time, subtract the quantity already on order.
EPQ, Quantity Discounts and Backorders
Q* = √[2·D·S / (H·(1 − d/p))]— Economic production quantity (units); d is demand rate and p production rate (same units, p > d), S set-up cost (₹/set-up).I_max = Q·(1 − d/p)— Maximum inventory in the EPQ model (units).TC* = √[2·D·S·H·(1 − d/p)]— Minimum annual set-up + holding cost (₹/year).TC(Q) = D·C + (D/Q)·S + (Q/2)·i·C— All-units discount total cost (₹/year); C is the price for Q's range, i carrying rate (fraction/year).Q* = √(2·D·S / H)·√[(H + B) / B]— EOQ with planned backorders (units); B is backorder cost (₹/unit·year).b* = Q*·H / (H + B)— Maximum backorder (units).
Safety Stock and Reorder Point under Uncertainty
ROP = d̄·L + z·σ_L— Reorder point (units); d̄ mean demand rate, L lead time, z normal deviate for the cycle service level (from tables), σ_L standard deviation of lead-time demand (units).σ_L = σ_d·√L— When demand varies (σ_d per period) and lead time is constant.σ_L = √(L̄·σ_d² + d̄²·σ_LT²)— When demand and lead time both vary; σ_LT is the standard deviation of lead time (periods).S = d̄·(T + L) + z·σ_d·√(T + L)— Order-up-to level for periodic review (units); T is the review period.
ABC and VED Analysis
ACVᵢ = Dᵢ·Cᵢ— Annual consumption value (₹/year); D annual usage (units/year), C unit cost (₹/unit). Rank by ACV and use cumulative % for ABC classes.% value = 100·ACVᵢ / ΣACV— Share of total value (%).
Just-in-Time and Kanban
N = D·(T_w + T_p)·(1 + α) / C— Number of kanbans (round up); D demand rate (units/time), T_w waiting time, T_p processing time (same time unit), α safety factor, C container size (units).Maximum inventory = N·C— Units in a kanban loop.
Lean Manufacturing and Value Stream Mapping
Takt time = available time / demand— Pace of customer demand (s/unit or min/unit).Minimum stations = total work content / takt time— Round up.WIP = throughput × lead time— Little's law; inventory pile lead time (days) = units / daily demand.PCE = value-added time / production lead time— Process cycle efficiency (dimensionless).
Supply Chain Management and ERP
Inventory turns = COGS / average inventory— Turns per year; days of supply = 365 / turns.Cash-to-cash cycle = days of inventory + days of receivables − days of payables— Days.Bullwhip ratio = Var(orders placed) / Var(demand received)— Dimensionless; > 1 means amplification upstream.SS_pooled = z·σ·√n— Safety stock when n identical independent markets are pooled (units), versus n·z·σ when held separately.