Operations Research

Operations Research — formula sheet

Production & Industrial Engineering · GATE PI · SI units. Drafted with Aria, checked by the AiCanCode.org team.

Linear Programming Formulation and Graphical Method

  • Objective: Max (or Min) Z = c₁x₁ + c₂x₂ + … + cₙxₙ — cⱼ = profit or cost per unit of activity xⱼ (₹/unit).
  • Constraint: aᵢ₁x₁ + … + aᵢₙxₙ (≤, =, ≥) bᵢ, xⱼ ≥ 0 — aᵢⱼ = resource i used per unit of xⱼ; bᵢ = resource available or required.
  • Intercepts of a constraint line: x₁ = bᵢ / aᵢ₁, x₂ = bᵢ / aᵢ₂ — for plotting.
  • Iso-profit slope: dx₂/dx₁ = −c₁ / c₂ — the optimum is at a corner point if a finite optimum exists.

Simplex Method: Big-M and Two-Phase

  • Net evaluation: Cj − Zj, with Zj = Σ C_B,i · aᵢⱼ — Max problem is optimal when all Cj − Zj ≤ 0; most positive enters.
  • Objective of a tableau: Z = Σ C_B,i · bᵢ.
  • Minimum ratio test: θ = min { bᵢ / aᵢₖ : aᵢₖ > 0 } — decides the leaving variable; no positive aᵢₖ means unbounded.
  • Big-M objective: Max Z = Σ cⱼxⱼ − M·ΣRᵢ or Min Z = Σ cⱼxⱼ + M·ΣRᵢ — Rᵢ = artificial variables, M very large.
  • Phase 1 objective: Min r = ΣRᵢ — r > 0 at the optimum means the LP is infeasible.

Duality and Sensitivity Analysis

  • Primal–dual pair: Max Z = cᵀx, Ax ≤ b, x ≥ 0 ⇔ Min W = bᵀy, Aᵀy ≥ c, y ≥ 0.
  • Weak duality: cᵀx ≤ bᵀy for any feasible x, y; strong duality: Z* = W*.
  • Complementary slackness: yᵢ · sᵢ = 0, xⱼ · tⱼ = 0 — sᵢ = primal slack, tⱼ = dual surplus.
  • Shadow price use: ΔZ = yᵢ · Δbᵢ — valid only inside the RHS feasibility range of bᵢ.
  • Reduced cost: c̄ⱼ = cⱼ − Σ aᵢⱼ yᵢ — a new activity is worth adding (Max) if c̄ⱼ > 0.

Transportation Problem

  • Model: Min Z = Σᵢ Σⱼ cᵢⱼ xᵢⱼ, Σⱼ xᵢⱼ = sᵢ, Σᵢ xᵢⱼ = dⱼ — balanced when Σ sᵢ = Σ dⱼ (else add a dummy row or column).
  • Basic cells: m + n − 1 — fewer occupied cells means degeneracy (add ε).
  • MODI: uᵢ + vⱼ = cᵢⱼ (occupied), dᵢⱼ = cᵢⱼ − (uᵢ + vⱼ) (empty) — optimal when all dᵢⱼ ≥ 0.
  • Cost change per loop: ΔZ = θ · dᵢⱼ — θ = smallest allocation on a minus corner.

Assignment Problem

  • Model: Min Z = Σᵢ Σⱼ cᵢⱼ xᵢⱼ, Σⱼ xᵢⱼ = 1, Σᵢ xᵢⱼ = 1, xᵢⱼ ∈ {0, 1} — n! possible assignments.
  • Hungarian test: minimum covering lines = n ⇒ optimal assignment exists on zeros; else subtract the smallest uncovered element k from uncovered cells and add k at line intersections.
  • Maximisation: lᵢⱼ = c_max − cᵢⱼ — convert profit to loss, then minimise.

Integer Programming: Branch and Bound

  • Relaxation bound: Z_IP ≤ Z_LP (Max), Z_IP ≥ Z_LP (Min).
  • Branching on fractional xⱼ = v: xⱼ ≤ ⌊v⌋ or xⱼ ≥ ⌊v⌋ + 1.
  • Fathom (Max): node infeasible, integer, or Z_node ≤ Z_incumbent.
  • Fixed-charge link: x ≤ U · y, y ∈ {0, 1} — U = upper limit on x.

Network Flow

  • Shortest Path (Dijkstra): d(v) = min{ d(v), d(u) + l(u, v) } — d = distance label, l = arc length (≥ 0); the smallest temporary label becomes permanent.
  • Minimal Spanning Tree: edges in a spanning tree = n − 1 — Kruskal or Prim; n = number of nodes.
  • Flow conservation: Σ f(i, k) = Σ f(k, j) at intermediate nodes, 0 ≤ f(i, j) ≤ c(i, j).
  • Maximal Flow: max flow = min cut capacity = min Σ c(i, j) over arcs from the source side to the sink side.

Project Networks: CPM and Floats

  • Forward pass: EF = ES + t, ES = max EF(predecessors); backward pass: LS = LF − t, LF = min LS(successors).
  • Total Float: TF = LS − ES = LF − EF (AOA: Lⱼ − Eᵢ − t) — critical activities have TF = 0.
  • Free Float: FF = min ES(successors) − EF (AOA: Eⱼ − Eᵢ − t).
  • Independent Float: IF = Eⱼ − Lᵢ − t (taken as 0 if negative); 0 ≤ IF ≤ FF ≤ TF.

PERT and Probability of Completion

  • Expected Time (TE): te = (a + 4m + b) / 6 — a = optimistic, m = most likely, b = pessimistic time.
  • Variance (σ²): σ² = ((b − a) / 6)².
  • Project mean and variance: Tₑ = Σ te, σ_T² = Σ σ² — critical-path activities only.
  • Probability: Z = (T_s − Tₑ) / σ_T, P(T ≤ T_s) = Φ(Z); due date for probability p: T_s = Tₑ + Z_p · σ_T.

Project Crashing and Time-Cost Trade-Off

  • Cost slope: S = (C_c − Cₙ) / (tₙ − t_c) — ₹/day; crash the cheapest critical activity first.
  • Total cost: C_T = Σ Cₙ + Σ S·Δt + c_i · T — c_i = indirect cost per day, T = duration.
  • Optimum duration: stop crashing when the cheapest daily crashing cost exceeds c_i.

Queuing Models: M/M/1 and M/M/c

  • M/M/1 Model: ρ = λ/μ, P₀ = 1 − ρ, Pₙ = (1 − ρ)ρⁿ, L = λ / (μ − λ), Lq = λ² / [μ(μ − λ)], W = 1 / (μ − λ), Wq = λ / [μ(μ − λ)] — λ = arrival rate, μ = service rate; needs ρ < 1.
  • M/M/c Model: r = λ/μ, ρ = λ/(cμ), P₀ = [Σ (n = 0 to c − 1) rⁿ/n! + r^c / (c!(1 − ρ))]⁻¹, Lq = P₀ r^c ρ / [c!(1 − ρ)²] — c = number of servers.
  • Little's law: L = λW, Lq = λWq, W = Wq + 1/μ.

Game Theory

  • Saddle point: max over i (min over j aᵢⱼ) = min over j (max over i aᵢⱼ) = V — pure strategies.
  • 2 × 2 mixed strategy: D = (a₁₁ + a₂₂) − (a₁₂ + a₂₁), p₁ = (a₂₂ − a₂₁)/D, q₁ = (a₂₂ − a₁₂)/D, V = (a₁₁a₂₂ − a₁₂a₂₁)/D — no saddle point.
  • Dominance: delete a row ≤ another row (player A); delete a column ≥ another column (player B).

Decision Theory Under Risk and Uncertainty

  • Hurwicz: H = α·(max payoff) + (1 − α)·(min payoff) — α = coefficient of optimism.
  • Regret: Rᵢⱼ = max over i (aᵢⱼ) − aᵢⱼ — minimax regret chooses the smallest maximum regret.
  • Expected monetary value: EMVᵢ = Σⱼ pⱼ aᵢⱼ; EOL: EOLᵢ = Σⱼ pⱼ Rᵢⱼ.
  • EVPI: EVPI = Σⱼ pⱼ · max over i (aᵢⱼ) − max EMV = min EOL.

Replacement Models

  • Average annual cost: A(n) = [C − S(n) + Σ R(t)] / n — C = price, S(n) = resale value, R(t) = running cost in year t; replace at the n giving minimum A(n).
  • Replacement rule: with constant or negligible resale value, replace at end of year n when R(n + 1) > A(n).
  • Group replacement: Nₖ = Σ (j = 0 to k − 1) Nⱼ p₍ₖ₋ⱼ₎, mean life t̄ = Σ k pₖ; individual cost per period (N₀/t̄)·c_i; group cost per period [N₀ c_g + c_i Σ (j = 1 to k) Nⱼ] / k.

Monte Carlo Simulation

  • Random-number ranges: value xₖ gets two-digit numbers from 100·F(xₖ₋₁) to 100·F(xₖ) − 1 — F = cumulative probability.
  • Estimate: x̄ = (1/n) Σ xᵢ, standard error s / √n — n = number of trials.
  • Exponential variate: x = −(1/λ) · ln(1 − r) — r = uniform random number in (0, 1).