Metrology, Quality and Reliability — formula sheet

Production & Industrial Engineering · GATE PI · SI units. Drafted with Aria, checked by the AiCanCode.org team.

Limits, Fits and Tolerances; Limit Gauge Design

  • T = UL − LL — Tolerance T (mm) of one part; UL, LL = upper and lower limits of size (mm).
  • ES = UL_hole − basic size, EI = LL_hole − basic size — Upper and lower deviations of a hole (mm); for a shaft use lower-case es, ei.
  • Maximum clearance = UL_hole − LL_shaft, Minimum clearance (allowance) = LL_hole − UL_shaft — A negative result is an interference (mm).
  • i = 0.45·∛D + 0.001·D — Standard tolerance unit i (µm); D (mm) = geometric mean √(D₁·D₂) of the diameter step; sizes up to 500 mm. IT grades are multiples of i (e.g. IT7 = 16i, IT8 = 25i).
  • Gauge tolerance ≈ 0.1 × work tolerance, Wear allowance ≈ 0.1 × gauge tolerance — Common conventions for limit-gauge design (Taylor's principle: GO gauge checks the maximum-material limit in full form, NO-GO the least-material limit at one point); use values stated in the question or standard.

Geometric Dimensioning and Tolerancing

  • Positional deviation (diametral) = 2·√(Δx² + Δy²) — Δx, Δy = measured deviations of the feature axis from true position (mm).
  • Bonus (hole) = actual size − MMC size, Bonus (shaft) = MMC size − actual size — Extra position tolerance available when the feature departs from MMC (mm).
  • Allowed position tolerance = stated tolerance at MMC + bonus (mm).
  • Virtual condition (hole) = MMC − geometric tolerance, Virtual condition (shaft) = MMC + geometric tolerance (mm).

Linear and Angular Measurement

  • LC (vernier) = 1 MSD − 1 VSD = s / n — Least count; s = main-scale division (mm), n = number of vernier divisions spanning (n − 1) main-scale divisions.
  • LC (micrometer) = p / N — p = screw pitch (mm), N = thimble divisions.
  • Reading = MSR + VC × LC − zero error — MSR = main-scale reading, VC = coinciding vernier division; a positive zero error is subtracted.
  • sin θ = h / L — Sine bar: h = slip-gauge stack height (mm), L = distance between roller centres (mm, e.g. 100 or 200).
  • dθ = dh / (L·cos θ) — Error in angle (rad) for an error dh in stack height; sine bars become inaccurate above about 45°.

Comparators and Interferometry

  • M = output movement / input movement — Magnification; for levers in series M = (l₁/l₂)·(l₃/l₄)…; optical lever M = 2D / x (D = scale distance, x = arm length).
  • h = n·λ/2 — Height difference h (µm) for n fringes with light of wavelength λ (µm); each fringe = λ/2.
  • h = (λ/2)·(n/l)·L — Height difference of two slip gauges compared with an optical flat: n fringes over length l of one gauge, L = distance between the gauges' contact points.

Surface Roughness Measurement

  • Ra = (1/L)·∫₀ᴸ |y| dx ≈ (1/n)·Σ|yᵢ| — Arithmetic mean deviation from the mean line (µm) over evaluation length L.
  • Rq = √[(1/n)·Σyᵢ²] — Root-mean-square roughness (µm).
  • Rz = (1/5)·ΣZᵢ — Mean of the peak-to-valley heights of five sampling lengths (µm).
  • Ra = (A₁ + A₂) / (L_chart · V) — From a recorded trace: A₁, A₂ = areas above and below the mean line on the chart, L_chart = chart length, V = vertical magnification (horizontal scale cancels if L_chart is on the same chart).
  • Rt ≈ f² / (8r), Ra ≈ Rt / 4 — Ideal turned surface with tool nose radius r and feed f (same length units); Rt/4 holds for an ideal symmetric triangular profile.

Measurement of Screw Threads and Gears

  • Lead = n_s · p — n_s = number of starts, p = pitch (mm).
  • d_best = p / [2·cos(θ/2)] — Best-size wire diameter; θ = included thread angle (for 60°: 0.5774·p).
  • E = M − d·[1 + cosec(θ/2)] + (p/2)·cot(θ/2) — Effective diameter by the three-wire method; M = measurement over wires, d = wire diameter (mm). For θ = 60°: E = M − 3d + 0.8660·p.
  • E = D − 0.6495·p — Basic effective (pitch) diameter of an ISO metric thread of major diameter D.
  • w = N·m·sin(90°/N), h = m·[1 + (N/2)·(1 − cos(90°/N))] — Gear tooth vernier: chordal tooth thickness w and chordal addendum h at the pitch circle; N = number of teeth, m = module (mm).
  • W = m·cos φ·[π·(S − 0.5) + N·inv φ], inv φ = tan φ − φ — Base tangent (span) length over S teeth; φ = pressure angle (rad in inv φ).

Coordinate Measuring Machines

  • L = √[(x₂ − x₁)² + (y₂ − y₁)² + (z₂ − z₁)²] — Distance between two measured points (mm).
  • D_bore = D_centres + d_ball, D_shaft = D_centres − d_ball — Probe-radius compensation; D_centres = diameter of the circle through recorded ball centres, d_ball = stylus ball diameter (mm).
  • ΔL = L·α·ΔT — Thermal length change (mm); α = coefficient of expansion (1/°C), ΔT = departure from 20 °C reference.
  • Minimum points: line 2, plane 3, circle 3, sphere 4, cylinder 5, cone 6 (more are needed to assess form).

Alignment Testing of Machine Tools

  • θ = h / L — Slope or angular misalignment (rad) from a deviation h over length L (same units); small angles.
  • h = n · S · L_b — Height difference across a spirit-level base; n = bubble divisions, S = sensitivity (mm/m per division ÷ 1000), L_b = base length (mm).
  • θ_div = l / R — Angle per vial division; l = division length, R = vial radius of curvature.
  • e = TIR / 2 — Eccentricity from the total indicator reading on a rotating feature.
  • d_axis = (r₀ + r₁₈₀) / 2 — True spindle-axis position from mandrel readings at 0° and 180°.
  • 1 rad = 206 265″; 0.01 mm/m ≈ 2.06″.

Quality Concepts and Cost of Quality

  • CoQ = C_P + C_A + C_IF + C_EF — Prevention + appraisal + internal failure + external failure costs (₹ per period).
  • CoQ % = CoQ / Sales × 100.
  • L(y) = k·(y − m)², k = A₀ / Δ₀² — Taguchi loss per part (₹); m = target, A₀ = loss at the customer tolerance Δ₀.
  • L̄ = k·[σ² + (ȳ − m)²] — Expected loss per part for a process with mean ȳ and standard deviation σ.

Control Charts for Variables: X-bar and R

  • X̿ = ΣX̄ᵢ / k, R̄ = ΣRᵢ / k — Grand mean and average range over k subgroups.
  • UCL = X̿ + A₂·R̄, LCL = X̿ − A₂·R̄ — X-bar chart limits; A₂ = 3/(d₂·√n).
  • UCL = D₄·R̄, LCL = D₃·R̄ — R chart limits.
  • σ̂ = R̄ / d₂, σ_X̄ = σ / √n — Process σ from ranges; standard deviation of subgroup means.
  • Factors: n = 4: A₂ = 0.729, D₃ = 0, D₄ = 2.282, d₂ = 2.059; n = 5: A₂ = 0.577, D₃ = 0, D₄ = 2.114, d₂ = 2.326 (other n from the SQC table).
  • ARL = 1 / p — Average run length; p = probability a point falls outside the limits (0.0027 for an in-control process with 3σ limits, ARL ≈ 370).

Control Charts for Attributes: p, np, c and u

  • p̄ = Σd / Σn, UCL/LCL = p̄ ± 3·√[p̄(1 − p̄)/n] — p chart (fraction defective); d = defectives, n = sample size.
  • UCL/LCL = n·p̄ ± 3·√[n·p̄(1 − p̄)] — np chart (number defective), constant n.
  • c̄ = Σc / k, UCL/LCL = c̄ ± 3·√c̄ — c chart (defects per inspection unit of constant size).
  • ū = Σc / Σn, UCL/LCL = ū ± 3·√(ū/n) — u chart (defects per unit, n may vary).
  • A negative LCL is set to 0.

Process Capability: Cp and Cpk

  • Cp = (USL − LSL) / (6σ) — Potential capability; USL, LSL = specification limits, σ = process standard deviation.
  • Cpk = min[(USL − μ)/(3σ), (μ − LSL)/(3σ)] — Actual capability; μ = process mean. Cpk ≤ Cp, equal only when centred.
  • Cpk = Cp·(1 − k), k = |M − μ| / [(USL − LSL)/2] — M = mid-point of the tolerance.
  • Cpm = (USL − LSL) / (6·√[σ² + (μ − T)²]) — Taguchi capability index; T = target.
  • Fraction above USL = 1 − Φ[(USL − μ)/σ] — Φ = standard normal CDF.

Acceptance Sampling: OC Curves, Single and Double Sampling

  • Pa = Σ(d = 0 to c) C(n, d)·pᵈ·(1 − p)ⁿ⁻ᵈ — Probability of acceptance, single plan (n, c), lot fraction defective p (binomial).
  • Pa ≈ Σ(d = 0 to c) e^(−λ)·λᵈ/d!, λ = n·p — Poisson approximation.
  • α = 1 − Pa(AQL), β = Pa(LTPD) — Producer's and consumer's risks.
  • AOQ = Pa·p·(N − n)/N — Average outgoing quality with rectifying inspection; N = lot size; AOQL = its maximum over p.
  • ATI = n + (1 − Pa)·(N − n) — Average total inspection per lot.
  • Pa = P(d₁ ≤ c₁) + Σ(c₁ < d₁ ≤ c₂) P(d₁)·P(d₂ ≤ c₂ − d₁), ASN = n₁ + n₂·P(c₁ < d₁ ≤ c₂) — Double sampling.

Reliability: Failure Rate, Bathtub Curve and MTBF

  • R(t) = 1 − F(t), h(t) = f(t) / R(t), R(t) = exp[−∫₀ᵗ h dt] — Reliability, hazard rate (h⁻¹), failure density f.
  • R(t) = e^(−λt), MTTF = 1/λ — Constant failure rate λ (h⁻¹); R(MTTF) = e⁻¹ = 0.368.
  • λ̂ = r / ΣTᵢ, MTBF = ΣTᵢ / r — r failures in total operating time ΣTᵢ (h).
  • h(interval) = n_f / (N_s·Δt) — Hazard from test data; N_s = survivors at the start of the interval.
  • A = MTBF / (MTBF + MTTR) — Inherent availability.
  • R(t) = exp[−(t/η)^β] — Weibull; β < 1 infant mortality, β = 1 constant, β > 1 wear-out; η = characteristic life.

Series, Parallel and Standby System Reliability

  • R_s = R₁·R₂·…·Rₙ, λ_s = Σλᵢ, MTTF_s = 1/Σλᵢ — Series system.
  • R_p = 1 − (1 − R₁)(1 − R₂)…(1 − Rₙ) — Active parallel; two identical exponential units: MTTF = 3/(2λ).
  • R = Σ(i = k to n) C(n, i)·Rⁱ·(1 − R)ⁿ⁻ⁱ — k-out-of-n; 2-out-of-3: R = 3R² − 2R³.
  • R_sb = e^(−λt)·(1 + λt), MTTF = 2/λ — Two identical units in cold standby, perfect switch; with switch reliability R_sw: R_sb = e^(−λt)·(1 + R_sw·λt).

Maintenance Planning and Total Productive Maintenance

  • MTBF = operating time / failures, MTTR = repair time / repairs (h).
  • OEE = Availability × Performance × Quality — Availability = operating time / planned production time; Performance = ideal cycle time × total count / operating time; Quality = good count / total count.
  • Bₙ = N·(p₁ + … + pₙ) + B₁·pₙ₋₁ + … + Bₙ₋₁·p₁ — Expected breakdowns in n periods after group preventive service of N machines; pᵢ = probability of failure in period i.
  • Cost per period = (N·c_pm + c_bd·ΣBᵢ) / n (PM every n periods); breakdown only: N·c_bd / Σ(i·pᵢ).

Total Quality Management and ISO 9001

  • ppm = nonconforming / supplied × 10⁶ — Parts per million defective.
  • Payback = project cost / annual saving, Annual saving = Δ(defect fraction) × annual volume × cost per defective.

Six Sigma and Quality Tools

  • DPU = D / U, DPO = D / (U·O), DPMO = DPO × 10⁶ — D = defects, U = units, O = opportunities per unit.
  • Sigma level ≈ z(1 − DPO) + 1.5 — With the conventional 1.5σ long-term shift; 6σ ↔ 3.4 DPMO, 4σ ↔ 6210 DPMO, 3σ ↔ 66 807 DPMO.
  • FPY ≈ e^(−DPU), RTY = FPY₁·FPY₂·…·FPYₖ — First-pass and rolled throughput yield.
  • RPN = S × O × D — FMEA risk priority number (each rating 1–10).