Metrology, CIM and Industrial Engineering — formula sheet
Mechatronics Engineering · GATE ME · SI units. Drafted with Aria, checked by the AiCanCode.org team.
Limits, Fits and Tolerances; GD&T Basics
Tolerance = Upper limit − Lower limit = ES − EI (hole) = es − ei (shaft)— permitted variation of a size; ES/EI, es/ei = upper/lower deviations of hole/shaft (μm or mm).Maximum clearance = Hole_max − Shaft_min;Minimum clearance (allowance) = Hole_min − Shaft_max— a negative value is interference.i = 0.45·∛D + 0.001·D— standard tolerance unit i (μm), D = geometric mean of the diameter step (mm),D = √(D₁·D₂); ISO system for sizes up to 500 mm.IT6 = 10i, IT7 = 16i, IT8 = 25i, IT9 = 40i, IT10 = 64i, IT11 = 100i— tolerance grades.Virtual condition (hole) = MMC size − geometric tolerance at MMC;Virtual condition (shaft) = MMC size + geometric tolerance at MMC.Bonus tolerance = |Actual size − MMC size|— extra geometric tolerance when the MMC modifier is used.
Linear and Angular Measurement, Comparators and Gauges
LC (vernier) = 1 MSD − 1 VSD = s / n— least count; s = value of one main-scale division (mm), n = number of vernier divisions.LC (micrometer) = p / N— p = screw pitch (mm), N = thimble divisions.sin θ = h / L— sine bar; h = slip-gauge height (mm), L = distance between roller centres (mm).Gauge tolerance T_g ≈ 0.1 × T_w;wear allowance W ≈ 0.1 × T_g— T_w = work tolerance (Taylor's principle gauge design).GO plug: H_min + W to H_min + W + T_g;NO-GO plug: H_max − T_g to H_max— H = hole limits.
Surface Finish, Interferometry and Alignment Testing
Ra = (1/L)·∫₀ᴸ |y| dx ≈ (1/n)·Σ|yᵢ|— arithmetic mean roughness (μm); yᵢ = ordinate from the mean line.Rq = √((1/n)·Σ yᵢ²)— RMS roughness (μm).Height change per fringe = λ / 2— optical flat or laser interferometer; λ = wavelength of light (μm).Displacement = N·λ / 2— N = fringes counted.Rmax = f² / (8r);Ra ≈ f² / (32r)— ideal turned surface; f = feed (mm/rev), r = nose radius (mm).
Coordinate Measuring Machines and Machine Vision Inspection
L = √((x₂ − x₁)² + (y₂ − y₁)² + (z₂ − z₁)²)— distance between two probed points (mm).E = A + L / K— CMM length-measuring error (μm); A, K = machine constants, L = measured length (mm).ΔL = L·α·(T − 20)— thermal expansion from the 20 °C reference; α = expansion coefficient (1/°C).Pixel size = FOV / number of pixels across the FOV— object-space resolution of a vision system.
NC and CNC Part Programming
N = 1000·V / (π·D)— spindle speed (rpm); V = cutting speed (m/min), D = diameter (mm).F = N·f(turning, drilling);F = N·z·f_z(milling) — feed rate (mm/min); f = feed per rev (mm), z = teeth, f_z = feed per tooth (mm).BLU = p / (n_s·G)— basic length unit (mm per pulse); p = lead-screw pitch (mm), n_s = steps per motor revolution, G = gear ratio (motor rev per screw rev).f_p = (F / p)·G·n_s / 60— pulse frequency (Hz), F in mm/min.
CAD/CAM, Group Technology and CAPP
[x′ y′ 1]ᵀ = T·[x y 1]ᵀ— 2D homogeneous transformation.R(θ) = [[cos θ, −sin θ, 0], [sin θ, cos θ, 0], [0, 0, 1]]— counter-clockwise rotation about the origin.P(u) = Σ C(n, i)·uⁱ·(1 − u)ⁿ⁻ⁱ·Pᵢ, 0 ≤ u ≤ 1— Bézier curve of degree n.V − E + F = 2— Euler's rule for a simple polyhedron.
Flexible Manufacturing Systems and Automated Material Handling
WLᵢ = Σ t·f·p— workload of station i (min per part); t = process time, f = operation frequency, p = part-mix fraction.Rp* = s* / WL*— maximum production rate at the bottleneck (the largest WLᵢ / sᵢ); s = number of servers.Uᵢ = (WLᵢ / sᵢ)·Rp*— utilisation of station i.Tc = TL + Ld / vc + TU + Le / ve— AGV delivery cycle time (min).nc = Rf / Rdv, rounded up — number of vehicles; Rf = deliveries required per hour, Rdv = deliveries per vehicle per hour.
Additive Manufacturing Processes
n = H / t— number of layers; H = part height, t = layer thickness (mm).c = t·cos θ— stair-step cusp height (mm); θ = angle between surface normal and build direction.E = P / (v·h·t)— volumetric energy density (J/mm³) in laser powder bed fusion; P = laser power (W), v = scan speed (mm/s), h = hatch spacing (mm).
Forecasting Methods
F(t+1) = (D(t) + … + D(t−n+1)) / n— n-period simple moving average.F(t+1) = α·D(t) + (1 − α)·F(t)— simple exponential smoothing, 0 ≤ α ≤ 1.F = a + b·t;b = (n·Σt·D − Σt·ΣD) / (n·Σt² − (Σt)²);a = D̄ − b·t̄— least-squares trend line.eₜ = Dₜ − Fₜ;MAD = Σ|eₜ| / N;MSE = Σeₜ² / N;TS = Σeₜ / MAD— forecast error measures and tracking signal.
Aggregate Planning, MRP and Scheduling
I(t) = I(t−1) + P(t) − D(t)— inventory balance per period.Net requirement = max(0, gross requirement − on-hand − scheduled receipts + safety stock)— MRP netting; planned order release is offset earlier by the lead time.Lateness Lᵢ = Cᵢ − dᵢ;Tardiness Tᵢ = max(0, Lᵢ)— C = completion time, d = due date. SPT minimises mean flow time; EDD minimises maximum lateness; Johnson's rule minimises makespan for two machines in series.
Inventory Models: EOQ, Quantity Discounts and Safety Stock
Q* = √(2DS / H)— economic order quantity (units); D = annual demand (units/year), S = ordering cost (₹/order), H = holding cost (₹/unit/year),H = i·C.TC = (D/Q)·S + (Q/2)·H + C·D— total annual cost; at Q*, ordering cost = holding cost and variable cost= √(2DSH).Q* = √(2DS / (H·(1 − d/p)));I_max = Q*·(1 − d/p)— production (EPQ) model; p = production rate > d = usage rate.ROP = d̄·L + SS— reorder point; d̄ = mean demand per day, L = lead time (days).SS = Z·σ_L,σ_L = σ_d·√L— safety stock; Z from the normal table for the service level (1.645 for 95%), σ_d = std. deviation of daily demand, constant lead time.
Linear Programming: Graphical and Simplex Methods
Max Z = Σ cⱼxⱼsubject toΣ aᵢⱼxⱼ ≤ bᵢ,xⱼ ≥ 0— standard LP.θ = min(bᵢ / aᵢₖ)over aᵢₖ > 0 — minimum ratio test for the leaving variable.Z* = W*— primal and dual optimal values are equal; shadow price = change in Z* per unit increase in bᵢ.
Transportation and Assignment Problems
Σ aᵢ = Σ bⱼ— balanced problem; otherwise add a dummy row or column.Basic cells = m + n − 1— non-degenerate basic feasible solution.uᵢ + vⱼ = cᵢⱼ(occupied cells);dᵢⱼ = cᵢⱼ − (uᵢ + vⱼ)(empty cells) — MODI; optimal for minimisation when all dᵢⱼ ≥ 0.
Network Models: PERT and CPM
ES_j = max(EF_i);EF = ES + t;LF_i = min(LS_j);LS = LF − t— forward and backward passes.TF = LS − ES;FF = min(ES of successors) − EF— total and free float.tₑ = (a + 4m + b) / 6;σ² = ((b − a) / 6)²— PERT expected time and variance; a, m, b = optimistic, most likely, pessimistic times.Z = (T_s − T_E) / √(Σσ²)— probability of meeting scheduled time T_s, summing over critical activities.Cost slope = (crash cost − normal cost) / (normal time − crash time)— ₹ per day for crashing.
Queuing Theory: Single-Server Models
ρ = λ / μ— utilisation; λ = arrival rate, μ = service rate (same time unit); requires ρ < 1.P₀ = 1 − ρ;Pₙ = (1 − ρ)·ρⁿ;P(N ≥ n) = ρⁿ.L = λ / (μ − λ);Lq = λ² / (μ(μ − λ))— mean number in system and in queue (M/M/1).W = 1 / (μ − λ);Wq = λ / (μ(μ − λ))— mean time in system and in queue.L = λ·W;Lq = λ·Wq— Little's law.Lq = ρ² / (2(1 − ρ))— M/D/1 (constant service time).
Statistical Quality Control and Control Charts
X̄ chart: X̿ ± A₂·R̄;R chart: UCL = D₄·R̄, LCL = D₃·R̄— A₂, D₃, D₄ from the SQC table for subgroup size n.X̄ chart with known σ: μ ± 3σ / √n.σ̂ = R̄ / d₂— process standard deviation estimate.p chart: p̄ ± 3·√(p̄(1 − p̄) / n);np chart: n·p̄ ± 3·√(n·p̄(1 − p̄));c chart: c̄ ± 3·√c̄— negative LCL is set to 0.Cp = (USL − LSL) / (6σ);Cpk = min[(USL − μ) / (3σ), (μ − LSL) / (3σ)]— process capability; Cpk ≤ Cp.