Plant Design and Economics — formula sheet
Chemical Engineering · GATE CH · SI units. Drafted with Aria, checked by the AiCanCode.org team.
Process Design Development and Flowsheets
X_sp = (A into reactor − A out of reactor) / A into reactor— single-pass conversion (–); based on reactor feed.X_overall = (A in fresh feed − A leaving process) / A in fresh feed— overall conversion (–); based on fresh feed.R = F·(1 − X_sp) / X_sp— recycle rate (kmol/h) for complete separation and total recycle of unreacted A, no purge; F = fresh feed (kmol/h).F·x_I,F = P·y_I,P— steady-state inert balance on a purged recycle loop; P = purge (kmol/h), x, y = inert mole fractions (–).
Plant Location and Plant Layout
Freight cost = Σ (mass × distance × freight rate)— ₹/yr; mass in t/yr, distance in km, rate in ₹/(t·km).Weighted score = Σ wᵢ·sᵢ— site rating; wᵢ = factor weights summing to 1, sᵢ = scores on a common scale.
Capital Investment: Fixed and Working Capital
TCI = FCI + WC— total capital investment (₹); FCI = fixed capital investment, WC = working capital.FCI = direct costs + indirect costs— direct: equipment, installation, piping, instrumentation, electrical, buildings, yard, services, land; indirect: engineering, construction expenses, legal, contractor's fee, contingency.TCI = FCI / (1 − w)— when working capital is a fraction w of TCI.WC = raw-material stock + product and in-process stock + receivables + cash − payables— component estimate (₹).
Cost Estimation Methods and Cost Indices
C₂ = C₁ × (I₂ / I₁)— cost updated from time 1 to time 2 (₹); I = cost index (–), given data.C_b = C_a × (Q_b / Q_a)ⁿ— capacity scaling; Q = capacity in the same unit; n ≈ 0.6 unless given (six-tenths rule).n = ln(C_b / C_a) / ln(Q_b / Q_a)— exponent from two costs at the same date.FCI = f_L × E— Lang method; E = delivered equipment cost (₹), f_L = Lang factor (given).
Estimation of Total Product Cost
Manufacturing cost = direct production costs + fixed charges + plant overhead— ₹/yr.Total Product Cost = Manufacturing Cost + General Expenses— ₹/yr; general expenses = administration, distribution and selling, R&D.TPC = A / (1 − g)— when items totalling a fraction g of TPC are included; A = sum of all other items (₹/yr).Unit cost = TPC / annual production— ₹/kg or ₹/t.
Time Value of Money: Interest and Annuities
F = P·(1 + i)ⁿ— compound amount; P present sum (₹), i rate per period (decimal), n periods.P = F / (1 + i)ⁿ— present worth of a future sum.i_eff = (1 + r/m)^m − 1— effective annual rate for nominal rate r compounded m times a year; continuous:i_eff = eʳ − 1.F = A·[(1 + i)ⁿ − 1] / i— future worth of an end-of-period annuity A (₹ per period).A = F·i / [(1 + i)ⁿ − 1]— sinking-fund deposit.P = A·[(1 + i)ⁿ − 1] / [i·(1 + i)ⁿ]— present worth of an annuity.A = P·i·(1 + i)ⁿ / [(1 + i)ⁿ − 1]— capital recovery (equal instalment repaying P).K = C_V + (C_V − S) / [(1 + i)ⁿ − 1]— capitalised cost; C_V first cost, S salvage (₹), n life (years).
Depreciation Methods
d = (V − S) / n— straight-line depreciation (₹/yr); V original cost, S salvage (₹), n life (years).d_k = f·B_(k−1),B_k = V·(1 − f)^k— declining balance; f fixed fraction (–), B_k book value after k years.f = 1 − (S / V)^(1/n)— Matheson fixed percentage reaching S after n years; double-declining balance usesf = 2/n.d_k = (V − S)·(n − k + 1) / [n(n + 1)/2]— sum-of-the-years-digits charge in year k.A = (V − S)·i / [(1 + i)ⁿ − 1],B_k = V − A·[(1 + i)^k − 1] / i— sinking-fund method.
Taxes, Insurance and Cash Flow
Gross profit = R − C_cash − D— ₹/yr; R revenue, C_cash cash costs (TPC excluding depreciation), D depreciation.Net profit = (1 − t)·(R − C_cash − D)— after income tax at rate t (decimal), for positive profit.Cash flow = Net profit + D = (1 − t)·(R − C_cash) + t·D— t·D is the depreciation tax shield.Cash flow = Net profit + D − ΔWC— when working capital increases by ΔWC during the year.
Profitability Analysis: Payback, ROI, NPV and IRR
Payback Period = depreciable fixed capital / (annual net profit + annual depreciation)— years; ignores time value of money.ROI = (average annual net profit / total capital investment) × 100— % per year.NPV = Σ CF_k / (1 + i)^k, k = 0 to n — CF_k cash flow in year k (₹, outlays negative), i = minimum acceptable rate (decimal).Σ CF_k / (1 + IRR)^k = 0— internal rate of return; interpolateIRR ≈ i₁ + (i₂ − i₁)·NPV₁ / (NPV₁ − NPV₂)between close rates.
Comparison of Alternatives and Replacement Analysis
EUAC = (P − S)·(A/P, i, n) + S·i + C_op— equivalent uniform annual cost (₹/yr); P first cost or, for an existing asset, its market value; C_op annual operating cost.(A/P, i, n) = i·(1 + i)ⁿ / [(1 + i)ⁿ − 1]— capital-recovery factor.Annual cost = (P − S) / n + C_op— straight-line approximation when interest is ignored.r_inc = annual saving / extra investment— incremental return on the more expensive alternative.
Optimum Design: Economic Pipe Diameter
ΔP = 8·f·L·ρ·Q² / (π²·D⁵)— Darcy–Weisbach at fixed volumetric flow Q (m³/s); f Darcy friction factor, L length (m), ρ density (kg/m³), D diameter (m).C_T = A·Dⁿ + B·D^(−m)— annual cost per metre: fixed charges on pipe plus pumping cost (m = 5 for constant f, ≈ 4.8 for smooth turbulent flow).D_opt = [m·B / (n·A)]^(1/(n + m))— economic diameter; at the optimum pumping cost / fixed charges = n/m.D_opt ≈ 0.363·Q^0.45·ρ^0.13— turbulent-flow correlation for steel pipe (SI: D in m, Q in m³/s, ρ in kg/m³); constant varies between sources.
Optimum Insulation Thickness and Optimum Reflux Ratio
x_opt = √(c_h·k·ΔT / c_i)— flat-wall economic thickness (m); k conductivity (W/m·K), ΔT surface-to-ambient difference (K), c_h cost of heat (₹ per W·yr), c_i annual fixed charges on insulation (₹ per m³·yr).x_opt = √(c_h·k·ΔT / c_i) − k/h— including an outside coefficient h (W/m²·K).V = (R + 1)·D— column vapour load; R reflux ratio L/D, D distillate rate.R_opt ≈ 1.1 to 1.5 × R_min— usual range of the optimum reflux ratio.
Break-even Analysis
Break-even Point (Units) = Fixed Costs / (Selling Price per Unit - Variable Cost per Unit)— units per year; costs in ₹/yr and ₹/unit.Q = [F + P_n / (1 − t)] / (s − v)— output for a target after-tax profit P_n (₹/yr); F fixed cost, s price, v variable cost per unit, t tax rate.Margin of safety = (Q − Q_BE) / Q— fraction of actual output above break-even.
Cost of Heat Exchangers, Columns and Reactors
C_p = C_b·(S / S_b)ⁿ·F_M·F_P·(I / I_b)— purchased cost from a base correlation; S size (area, volume or weight), F_M material and F_P pressure factors (given data), I cost index.W = π·D·H·t·ρ_m— cylindrical shell weight (kg); t wall thickness (m), ρ_m metal density (kg/m³).N_actual = N_theoretical / E_o— actual trays; E_o overall tray efficiency (–).C_BM = F_BM·C_p— installed (bare-module) cost; F_BM given.
Hazard Identification: HAZOP and HAZAN
R = F·C— risk as frequency (per yr) × consequence per event.F_top = D·p— AND gate: demand rate D (per yr) on a protective layer with failure probability p (–); OR gate of rare independent events:F ≈ F₁ + F₂.fdt ≈ f·T / 2— fractional dead time of a tested trip; f unrevealed failure rate (per yr), T test interval (yr); two independent trips:fdt ≈ (f·T)² / 3.H = D·fdt— hazard rate (per yr).
Environmental and Safety Considerations in Plant Design
m = C·Q— pollutant load (g/day); C concentration (mg/L = g/m³), Q flow (m³/day).η = 1 − C_out / C_in— removal efficiency; units in series:η = 1 − (1 − η₁)(1 − η₂)….Atom economy = M_product / Σ M_reactants × 100— % from the stoichiometric equation (molar masses × coefficients).E-factor = mass of waste / mass of product— (–).