Plant Design and Economics

Plant Design and Economics — formula sheet

Chemical Engineering · GATE CH · SI units. Drafted with Aria, checked by the AiCanCode.org team.

Process Design Development and Flowsheets

  • X_sp = (A into reactor − A out of reactor) / A into reactor — single-pass conversion (–); based on reactor feed.
  • X_overall = (A in fresh feed − A leaving process) / A in fresh feed — overall conversion (–); based on fresh feed.
  • R = F·(1 − X_sp) / X_sp — recycle rate (kmol/h) for complete separation and total recycle of unreacted A, no purge; F = fresh feed (kmol/h).
  • F·x_I,F = P·y_I,P — steady-state inert balance on a purged recycle loop; P = purge (kmol/h), x, y = inert mole fractions (–).

Plant Location and Plant Layout

  • Freight cost = Σ (mass × distance × freight rate) — ₹/yr; mass in t/yr, distance in km, rate in ₹/(t·km).
  • Weighted score = Σ wᵢ·sᵢ — site rating; wᵢ = factor weights summing to 1, sᵢ = scores on a common scale.

Capital Investment: Fixed and Working Capital

  • TCI = FCI + WC — total capital investment (₹); FCI = fixed capital investment, WC = working capital.
  • FCI = direct costs + indirect costs — direct: equipment, installation, piping, instrumentation, electrical, buildings, yard, services, land; indirect: engineering, construction expenses, legal, contractor's fee, contingency.
  • TCI = FCI / (1 − w) — when working capital is a fraction w of TCI.
  • WC = raw-material stock + product and in-process stock + receivables + cash − payables — component estimate (₹).

Cost Estimation Methods and Cost Indices

  • C₂ = C₁ × (I₂ / I₁) — cost updated from time 1 to time 2 (₹); I = cost index (–), given data.
  • C_b = C_a × (Q_b / Q_a)ⁿ — capacity scaling; Q = capacity in the same unit; n ≈ 0.6 unless given (six-tenths rule).
  • n = ln(C_b / C_a) / ln(Q_b / Q_a) — exponent from two costs at the same date.
  • FCI = f_L × E — Lang method; E = delivered equipment cost (₹), f_L = Lang factor (given).

Estimation of Total Product Cost

  • Manufacturing cost = direct production costs + fixed charges + plant overhead — ₹/yr.
  • Total Product Cost = Manufacturing Cost + General Expenses — ₹/yr; general expenses = administration, distribution and selling, R&D.
  • TPC = A / (1 − g) — when items totalling a fraction g of TPC are included; A = sum of all other items (₹/yr).
  • Unit cost = TPC / annual production — ₹/kg or ₹/t.

Time Value of Money: Interest and Annuities

  • F = P·(1 + i)ⁿ — compound amount; P present sum (₹), i rate per period (decimal), n periods.
  • P = F / (1 + i)ⁿ — present worth of a future sum.
  • i_eff = (1 + r/m)^m − 1 — effective annual rate for nominal rate r compounded m times a year; continuous: i_eff = eʳ − 1.
  • F = A·[(1 + i)ⁿ − 1] / i — future worth of an end-of-period annuity A (₹ per period).
  • A = F·i / [(1 + i)ⁿ − 1] — sinking-fund deposit.
  • P = A·[(1 + i)ⁿ − 1] / [i·(1 + i)ⁿ] — present worth of an annuity.
  • A = P·i·(1 + i)ⁿ / [(1 + i)ⁿ − 1] — capital recovery (equal instalment repaying P).
  • K = C_V + (C_V − S) / [(1 + i)ⁿ − 1] — capitalised cost; C_V first cost, S salvage (₹), n life (years).

Depreciation Methods

  • d = (V − S) / n — straight-line depreciation (₹/yr); V original cost, S salvage (₹), n life (years).
  • d_k = f·B_(k−1), B_k = V·(1 − f)^k — declining balance; f fixed fraction (–), B_k book value after k years.
  • f = 1 − (S / V)^(1/n) — Matheson fixed percentage reaching S after n years; double-declining balance uses f = 2/n.
  • d_k = (V − S)·(n − k + 1) / [n(n + 1)/2] — sum-of-the-years-digits charge in year k.
  • A = (V − S)·i / [(1 + i)ⁿ − 1], B_k = V − A·[(1 + i)^k − 1] / i — sinking-fund method.

Taxes, Insurance and Cash Flow

  • Gross profit = R − C_cash − D — ₹/yr; R revenue, C_cash cash costs (TPC excluding depreciation), D depreciation.
  • Net profit = (1 − t)·(R − C_cash − D) — after income tax at rate t (decimal), for positive profit.
  • Cash flow = Net profit + D = (1 − t)·(R − C_cash) + t·D — t·D is the depreciation tax shield.
  • Cash flow = Net profit + D − ΔWC — when working capital increases by ΔWC during the year.

Profitability Analysis: Payback, ROI, NPV and IRR

  • Payback Period = depreciable fixed capital / (annual net profit + annual depreciation) — years; ignores time value of money.
  • ROI = (average annual net profit / total capital investment) × 100 — % per year.
  • NPV = Σ CF_k / (1 + i)^k, k = 0 to n — CF_k cash flow in year k (₹, outlays negative), i = minimum acceptable rate (decimal).
  • Σ CF_k / (1 + IRR)^k = 0 — internal rate of return; interpolate IRR ≈ i₁ + (i₂ − i₁)·NPV₁ / (NPV₁ − NPV₂) between close rates.

Comparison of Alternatives and Replacement Analysis

  • EUAC = (P − S)·(A/P, i, n) + S·i + C_op — equivalent uniform annual cost (₹/yr); P first cost or, for an existing asset, its market value; C_op annual operating cost.
  • (A/P, i, n) = i·(1 + i)ⁿ / [(1 + i)ⁿ − 1] — capital-recovery factor.
  • Annual cost = (P − S) / n + C_op — straight-line approximation when interest is ignored.
  • r_inc = annual saving / extra investment — incremental return on the more expensive alternative.

Optimum Design: Economic Pipe Diameter

  • ΔP = 8·f·L·ρ·Q² / (π²·D⁵) — Darcy–Weisbach at fixed volumetric flow Q (m³/s); f Darcy friction factor, L length (m), ρ density (kg/m³), D diameter (m).
  • C_T = A·Dⁿ + B·D^(−m) — annual cost per metre: fixed charges on pipe plus pumping cost (m = 5 for constant f, ≈ 4.8 for smooth turbulent flow).
  • D_opt = [m·B / (n·A)]^(1/(n + m)) — economic diameter; at the optimum pumping cost / fixed charges = n/m.
  • D_opt ≈ 0.363·Q^0.45·ρ^0.13 — turbulent-flow correlation for steel pipe (SI: D in m, Q in m³/s, ρ in kg/m³); constant varies between sources.

Optimum Insulation Thickness and Optimum Reflux Ratio

  • x_opt = √(c_h·k·ΔT / c_i) — flat-wall economic thickness (m); k conductivity (W/m·K), ΔT surface-to-ambient difference (K), c_h cost of heat (₹ per W·yr), c_i annual fixed charges on insulation (₹ per m³·yr).
  • x_opt = √(c_h·k·ΔT / c_i) − k/h — including an outside coefficient h (W/m²·K).
  • V = (R + 1)·D — column vapour load; R reflux ratio L/D, D distillate rate.
  • R_opt ≈ 1.1 to 1.5 × R_min — usual range of the optimum reflux ratio.

Break-even Analysis

  • Break-even Point (Units) = Fixed Costs / (Selling Price per Unit - Variable Cost per Unit) — units per year; costs in ₹/yr and ₹/unit.
  • Q = [F + P_n / (1 − t)] / (s − v) — output for a target after-tax profit P_n (₹/yr); F fixed cost, s price, v variable cost per unit, t tax rate.
  • Margin of safety = (Q − Q_BE) / Q — fraction of actual output above break-even.

Cost of Heat Exchangers, Columns and Reactors

  • C_p = C_b·(S / S_b)ⁿ·F_M·F_P·(I / I_b) — purchased cost from a base correlation; S size (area, volume or weight), F_M material and F_P pressure factors (given data), I cost index.
  • W = π·D·H·t·ρ_m — cylindrical shell weight (kg); t wall thickness (m), ρ_m metal density (kg/m³).
  • N_actual = N_theoretical / E_o — actual trays; E_o overall tray efficiency (–).
  • C_BM = F_BM·C_p — installed (bare-module) cost; F_BM given.

Hazard Identification: HAZOP and HAZAN

  • R = F·C — risk as frequency (per yr) × consequence per event.
  • F_top = D·p — AND gate: demand rate D (per yr) on a protective layer with failure probability p (–); OR gate of rare independent events: F ≈ F₁ + F₂.
  • fdt ≈ f·T / 2 — fractional dead time of a tested trip; f unrevealed failure rate (per yr), T test interval (yr); two independent trips: fdt ≈ (f·T)² / 3.
  • H = D·fdt — hazard rate (per yr).

Environmental and Safety Considerations in Plant Design

  • m = C·Q — pollutant load (g/day); C concentration (mg/L = g/m³), Q flow (m³/day).
  • η = 1 − C_out / C_in — removal efficiency; units in series: η = 1 − (1 − η₁)(1 − η₂)….
  • Atom economy = M_product / Σ M_reactants × 100 — % from the stoichiometric equation (molar masses × coefficients).
  • E-factor = mass of waste / mass of product — (–).